New Delhi, November 2026 : India’s first bullet train project is approaching a major milestone, with trial runs on the 50-km Surat-Bilimora section of the Mumbai-Ahmedabad High-Speed Rail Corridor expected to begin in May 2027, Railway Minister Ashwini Vaishnaw said on Monday.
The Surat-Bilimora stretch will be the first section of the country's maiden high-speed rail corridor to undergo testing, marking a significant step towards the launch of bullet train services.
Vaishnaw said signalling work on the section is expected to be completed by January 2027, while electrification has already been finished. The overhead equipment was energised on November 20 across both the up and down lines of the elevated alignment.
The corridor will operate on a 2x25 kV traction system. Installation work at the Bilimora traction substation has also been completed, the minister said.
The Mumbai-Ahmedabad project will be commissioned in phases. The Ahmedabad-Vapi section is targeted for completion by the end of 2027, while services are expected to extend up to Thane by 2029.
Initial trials will use the B-28 train, which has been designed to operate at speeds of up to 280 kmph. Vaishnaw explained that trains travelling above 240 kmph fall within the high-speed rail category and require specialised engineering and construction standards.
One of the major technical challenges is managing pressure conditions generated when trains move at such high speeds. Both the train and the supporting infrastructure must be designed to withstand considerable pressure forces.
The minister said the B-28 train had successfully cleared the squeeze test. During this test, it was subjected to pressure levels twice the atmospheric pressure expected during regular operations, demonstrating its ability to withstand demanding operating conditions.
Vaishnaw also said construction on the Maharashtra section of the corridor, including the undersea tunnel, was progressing well.
Last week, the minister said the 508-km Mumbai-Ahmedabad High-Speed Rail Corridor had moved beyond the planning stage, with construction advancing on the ground. The first high-speed rail service is targeted to begin operations in the last quarter of 2027.
Describing the project as one of India's most ambitious infrastructure initiatives, Vaishnaw said it would significantly reduce travel time between Mumbai and Ahmedabad, two major economic centres.
“India’s first bullet train is no longer an announcement. It is 508 km of construction, moving at full pace. The first service begins in the last quarter of 2027!” he said in a statement on November 20.
The planned May 2027 trials on the Surat-Bilimora section will be an important test of the train and corridor systems ahead of the phased commissioning of the country's first bullet train service.