Panaji, November 2026: The Goa government has notified amendments to the Goa Land Development and Building Construction Regulations, 2026, allowing eligible developments across the state to avail themselves of additional Floor Area Ratio (FAR) and greater building heights, subject to specified conditions.
The government informed the High Court of Bombay at Goa on Wednesday that the amendments were published in the Extraordinary Official Gazette by the Department of Town and Country Planning on November 24 and came into force with immediate effect.
Under the newly introduced Regulation 6.1.2, the government can grant additional FAR and building height on the recommendation of the Town and Country Planning (TCP) Board. The provision covers developments in municipal, planning and village areas, provided the plot has a minimum area of 300 square metres.
Annexure XIII-A specifies the additional development potential based on the existing permissible FAR and the width of the adjoining road, with categories ranging from six metres to 10 metres and above. The maximum total FAR has been capped at 300, calculated on the total net effective plot area, while the maximum permissible building height is 40 metres. In certain lower-FAR zones along roads measuring between six and 10 metres, a stricter height ceiling of 14.9 metres will apply.
Eligible Zones and Exemptions
The concessions cover residential and settlement, commercial, public and semi-public, institutional, transport, warehousing, communication and industrial zones. However, Goa Industrial Development Corporation estates and industrial areas have been kept outside the scope of the amendments.
Four- and five-star hotel projects will not qualify for the additional FAR and height benefits. Developers proposing projects on plots measuring 500 square metres or more along roads at least eight metres wide must submit a notarised affidavit undertaking that the additional development potential will not be used to establish such hotels.
Developments falling within protected monument buffer zones are also excluded. Coastal Regulation Zone areas will continue to be governed by the applicable coastal regulations.
Safety and Infrastructure Requirements
Developers seeking the concessions must pay the prescribed fees before obtaining technical clearance. They must also comply with requirements relating to setbacks, structural safety, the load-bearing capacity of existing buildings and additional parking facilities.
A No Objection Certificate from the Fire and Emergency Services Department will be mandatory before applying for a construction licence.
The amended regulations also make rainwater harvesting compulsory for all projects. In addition, solar photovoltaic systems and/or solar water-heating facilities must be installed to cover at least five per cent of the sanctioned electrical load.
Projects consuming more than 9.7 kilolitres of water daily in areas without sewerage facilities must install sewage treatment plants. The government, however, may relax this requirement for proposals that had received approval earlier.
The High Court has scheduled the matter for further hearing on January 19.