Hyderabad, November 2026 : The Telangana Real Estate Regulatory Authority (TG RERA) has imposed penalties totalling approximately ₹2.13 crore on real estate developers for statutory violations across multiple residential projects. In a series of orders issued on November 25, the authority also directed developers to issue refunds, pay interest for delayed possession, complete pending infrastructure and obtain occupancy certificates.
The highest penalty of ₹2 crore was imposed on Aliens Developers Private Limited in connection with its Aliens Space Station Township project at Tellapur in Sangareddy district.
Acting on complaints filed by A. Nagalakshmi and V. Nagarjun Yadav, TG RERA found that the developer had collected more than 10 per cent of the property value without executing a registered agreement for sale, in violation of Section 13 of the Real Estate (Regulation and Development) Act, 2016. The authority also observed that the draft agreement submitted by the company contained provisions inconsistent with statutory requirements, including those relating to compensation for delayed possession.
The developer has been directed to pay the penalty within 60 days and provide a legally compliant agreement within seven days. If it fails to specify a definite possession date and the purchasers choose to withdraw, it must refund ₹42,11,898 with interest at 10.85 per cent per annum.
In another ruling, TG RERA ordered the initiation of suo motu proceedings against Bhuvanteza Infra Projects Private Limited and Green Metro Infratech Projects Private Limited over the sale of flats in the Tulasi Bhagyanagar project at Dundigal before obtaining the required approvals and registration.
Four purchasers had collectively paid ₹1.36 crore, including ₹96 lakh collected from three buyers before the necessary approvals and registration were secured. Holding both companies jointly and severally responsible, the authority directed them to pay delayed possession interest at 10.85 per cent per annum, complete pending amenities, obtain the occupancy certificate and hand over the flats.
TG RERA also imposed a penalty of ₹10,06,916 on Akshita Infra for promotional material relating to its Akshita Heights plotted development. The project was advertised as a gated layout, although the boundary wall was not included in the sanctioned plan.
ELV Developers was fined ₹3,20,339 for collecting advances beyond the statutory limit without executing a registered agreement for sale. It was also directed to pay interest on amounts subsequently refunded to the purchaser.
In a separate case, Alekya Infra Developers was ordered to refund ₹17,42,250 with interest after a plot in its NSR County Phase II project was sold to a third party.
The authority issued further directions in other cases. Vasavi Realtors LLP was ordered to pay delayed possession interest to buyers in Vasavi Lake City, while Bharati Builders was directed to refund ₹9.30 lakh each in two complaints concerning Bharathi's Lake View Apartments at Kompally.
In five complaints relating to ELV Cosmopolis at Adibatla, ELV Projects Private Limited was instructed to complete pending construction and provide essential amenities within six months. It must also obtain an occupancy certificate within three months of completing the work.
TG RERA issued additional directions concerning electricity infrastructure, parking allotments and the formation of associations of allottees in other residential developments. The orders underline the authority's focus on compliance with registration, disclosure, possession and project-delivery requirements under the real estate regulatory framework.