Dehradun, Nov 2026 : Uttarakhand Chief Minister Pushkar Singh Dhami on Friday reviewed the physical and financial progress of major infrastructure projects, including the Haridwar Ganga Corridor, Rishikesh Ganga Corridor and Sharda Riverfront Corridor. Chairing the fifth meeting of the Uttarakhand Investment and Infrastructure Development Board (UIIDB) at the Chief Minister's residence, he directed officials to accelerate ongoing works and complete the necessary formalities for projects that could be started soon.
Dhami said that visible progress on some projects should be achieved within the next month. He instructed all concerned departments to work in coordination to ensure timely implementation.
The Chief Minister emphasised that infrastructure projects should reflect the identity, culture and religious and natural significance of their respective regions. He said local characteristics must be incorporated into development plans so that the distinct identity of each area is preserved while tourism and employment opportunities are expanded.
Haridwar Ganga Corridor: Projects Worth Rs 3,297 Crore
Officials informed the meeting that projects worth Rs 3,297 crore have been proposed under the Haridwar Ganga Corridor. Of these, projects worth approximately Rs 495 crore are currently at the implementation stage.
Progress has been recorded across several key locations. Around 75 per cent of the work on the development of the administrative route has been completed. Development works in the northern area of Har Ki Pauri have reached 70 per cent completion, while the redevelopment of Har Ki Pauri and Subhash Ghat is 50 per cent complete.
The redevelopment work in the Rodi Belwala area has reached 45 per cent completion. Similarly, development of the access routes to Maa Mansa Devi and Maa Chandi Devi temples has achieved 55 per cent and 50 per cent progress, respectively.
These works are targeted for completion by December 2026. Meanwhile, 30 per cent of the redevelopment work at Sati Kund has been completed, with the project scheduled for completion by April 2027.
Rishikesh Ganga Corridor: Projects Worth Rs 3,456 Crore
Under the Rishikesh Ganga Corridor, projects worth Rs 3,456 crore have been proposed, of which projects valued at Rs 274 crore are currently being implemented.
The construction of an Integrated Command and Control Centre near Janki Setu has achieved 39 per cent progress. The facility is targeted for completion by June 2027.
Other ongoing projects include the development of Triveni Ghat at a cost of Rs 115.07 crore, beautification of the Aastha Path at Rs 35.78 crore and construction of the Chandrabhaga pedestrian bridge at Rs 32.28 crore.
Development work is also underway to improve rafting-related infrastructure and tourist facilities in the Shivpuri and Neer Beach areas. These initiatives are intended to strengthen tourism infrastructure and improve facilities for visitors.
Sharda Riverfront Corridor: Projects Worth Rs 1,526 Crore
Projects worth Rs 1,526 crore have been proposed under the Sharda Riverfront Corridor, with works valued at Rs 340.49 crore currently under implementation.
As part of efforts to reduce disaster risks, an ecological corridor is being developed at a cost of Rs 85.23 crore. Around 75 per cent of this work has been completed.
The redevelopment of Sharda Ghat, being undertaken at a cost of Rs 184.20 crore, has achieved 30 per cent progress. Meanwhile, the first phase of the urban drainage project, costing Rs 66.49 crore, is 13 per cent complete.
Construction of the Tanakpur bus terminal has also reached its final stage.
Three Corridors Expected to Generate Employment
The meeting was informed that projects worth a combined Rs 8,279 crore have been proposed under the three corridors. Of this total, projects worth approximately Rs 1,109 crore are currently at the implementation stage.
These projects are expected to generate direct employment for between 21,000 and 27,000 people and indirect employment for around 45,000 to 53,000 people.
The meeting also reviewed progress on a proposal to develop a Spiritual Economic Zone across approximately 72 hectares in the Srinagar-Belakedar area.
In addition, discussions were held on proposals relating to the safe and planned development of adventure tourism, expansion of tourist facilities, promotion of private investment and effective monitoring of infrastructure projects.
Dhami stressed the need for coordinated efforts among departments to ensure that ongoing projects progress faster and new initiatives move towards implementation without unnecessary delays. He also underlined the importance of incorporating local cultural and geographical features into infrastructure development.
The review covered projects aimed at improving pilgrimage facilities, urban infrastructure, tourism connectivity, disaster resilience and employment opportunities. Their timely and quality implementation will be important in delivering the intended benefits to residents, visitors and local businesses across the state.