Chief Minister Dr. Mohan Yadav visited the Greenko Power Plant at Rampura in Neemuch district following the Cabinet meeting at Gandhi Sagar in Mandsaur district. He inaugurated one unit of the project by pressing a button. Chief Minister Dr. Yadav said that hydropower plants and pumped hydro storage represented emerging technologies in the power generation sector.
The Gandhi Sagar Pumped Hydro Storage Project had been developed at a cost of ₹11,474 crore. Once fully operational, it would generate 2,000 MW of electricity during peak demand hours, enabling immediate power supply as per requirements. This would help ensure adequate electricity availability in the State round the clock.
Asia’s Largest Standalone Pumped Hydro Storage Project
The Greenko Group is investing approximately ₹11,500 crore in the 1,920 MW Gandhi Sagar Pumped Hydro Storage Project in Neemuch district. Once completed, the project will be capable of generating 1,920 MW of electricity continuously for six hours at full capacity. It is being established in Khemala Block of Rampura Tehsil in Neemuch district, over an area of approximately 414 hectares. It is the largest standalone pumped hydro storage project under construction in India and across Asia.
The project comprises two reservoirs. The existing Gandhi Sagar Reservoir, with a total capacity of approximately 270 TMC (7,643.70 MCM), will serve as the lower reservoir. Only 2.4 TMC (67.66 MCM) of water from Gandhi Sagar will be used for the project. The water will not be consumed but will be recycled and reused in a closed-loop system.
In pumping mode, surplus solar or wind energy available from the grid during the day or night will be used to pump water from the lower reservoir to the upper reservoir through reversible motor-pump units for energy storage. In turbine mode, during periods of high electricity demand or peak hours, water will be released from the upper reservoir to the lower reservoir. This will drive the turbines to generate electricity for supply to the grid.
The project can generate electricity at its full capacity of 1,920 MW continuously for six hours. Its rated head in turbine mode is approximately 122 metres. The round-trip efficiency, or the capacity to return stored energy, is estimated at around 80 per cent. A total of nine turbines are being installed, with an annual energy generation capacity of 3,580 million units. For pumping operations and evacuation of generated power, the project is connected to the 765/400 kV PGCIL/CTU substation located in Mandsaur district, approximately 60 km away.
Commercial operations of the entire project are scheduled to commence in June 2027. Approximately 4,000 people have received employment during the construction phase. Once operations and maintenance activities begin, the project is expected to generate permanent employment and contribute to the economy of the region and the State.
Presentation Made Before CM and Cabinet Ministers
A presentation on the power plant was made before Chief Minister Dr. Yadav at the Greenko conference hall. The Chief Minister also inspected the project viewpoint, turbines and power house, and received detailed technical information about the project.