Gauhati High Court Seeks RIPPL’s Assurance Regarding The Completion Of NH 29 By March 2027.

Listen to this story
Gauhati High Court Seeks RIPPL’s Assurance Regarding The Completion Of NH 29 By March 2027.

Dimapur; November 2026: The Kohima Bench of Gauhati High Court has directed M/S Ratna Infrastructure Projects Pvt. Ltd. (RIPPL) – the contractor assigned with the development of Package-II of the two-lane NH-29 Kohima–Jessami Road, to categorically state what steps it has taken with regard to the deployment of sufficient machinery and manpower at the project site, and indicate whether it can achieve completion by March 01, 2027, which at present is progressing by less than 02% over the past month.

Allowing Ratna Infrastructure Projects Pvt. Ltd. until November 25 to file its response, a division bench of Justice Robin Phukan and Justice Yarenjungla Longkumer issued the direction after considering affidavits from the Authority Engineer and the National Highways and Infrastructure Development Corporation Ltd. (NHIDCL) raising concerns over slow progress of the work and inadequate mobilisation of resources.

Figures exhibited before the court showed physical progress on the 21.90-km stretch stood at approximately 46.98% and financial progress at 45.55% up to October 2026, compared to 45.11% physical and 43.63% financial progress reported at the previous hearing on September 30. Despite repeated directions to mobilise adequate machinery, manpower and materials, progress achieved during the preceding month was less than 02%, the Authority Engineer have stated.

Tracing the project’s timeline, the Authority Engineer’s affidavit recorded that the first contractor had been terminated when physical progress stood at 58.08% and financial progress at 54.08%. After the balance work was awarded to Ratna Infrastructure Projects through a letter of award dated October 10, 2023, the firm achieved physical progress of only about 4.70% between the appointed date and January 2025, a period of approximately one year.

Although an extension of time up to March 1, 2027 was granted via a letter dated September 18, 2026, the Authority Engineer stated that the contractor had repeatedly been directed to expedite the work within the approved extended completion period.

In its separate affidavit filed today (Wednesday – 18th November) NHIDCL stated that several notices had been issued to the contractor over its continuous failure to maintain the required rate of progress in accordance with the approved construction programme and contractual milestones, adding that the firm had failed to mobilise adequate resources at the project site till date.

The court is hearing a public interest litigation filed by the Chakhesang Public Organisation and another petitioner. At the previous hearing on September 30, the bench had directed the Authority Engineer to file an affidavit explaining the reasons for the delay and to remain personally present. The matter has been listed for November 25, with the Authority Engineer directed to remain present on the next date.

Earlier, on the 02nd of this month (November 2026) – RIPPL had assured the Joint Action Committee (JAC) of National Highway-29 (NH-29) Kohima-Jessami Road that the ongoing road construction work will be completed by May 15, 2027, following a joint physical inspection of Package-II from Chakhabama to Kikruma on Monday (02nd November 2026).

According to a press statement issued by the JAC media cell, the assurance was given by RIPPL’s authorised signatory for the project, Dr. MSN Murthy, during a meeting held after the inspection. He said that the practical difficulties and issues concerning the Ministry of Road Transport and Highways (MoRTH) had been resolved and that large-scale construction work would resume shortly after November 15. He had also urged the public to cooperate with the company.

The inspection was conducted under the initiative of the JAC, with participation from RIPPL officials and representatives of frontal organisations from Kohima, Phek, Meluri and Kiphire districts, along with leaders from Kikruma and Kezoma villages. The team began its inspection at RIPPL’s stone plant quarry site in Chakhabama and concluded at the company’s base camp in Kikruma, followed by an official meeting.

Addressing the meeting, JAC convenor Vivolie Kezo expressed concern over what he described as NHIDCL’s lack of commitment to the execution of the NH-29 Kohima-Jessami Road project, particularly the Chakhabama-Kikruma stretch. He had alleged that repeated extensions had been granted for the project without adequate progress, while public concerns remained unaddressed. Kezo had urged the National Highways and Infrastructure Development Corporation Limited (NHIDCL) to approach the project with the seriousness and sincerity it deserved before any untoward incident occurred. He stated that RIPPL was awarded the project on January 5, 2024, with a scheduled completion date of January 4, 2026. However, he alleged that the contractor had repeatedly sought extensions instead of completing the work within the stipulated timeframe.

He also raised concerns over the quality of work, claiming it did not meet tender specifications, and pointed to the reported lack of adequate machinery, manpower and raw materials. He further cited issues such as frequent fuel shortages and delays in salary payments to staff as factors contributing to the slow progress. Kezo had urged Murthy to address the concerns of the people sincerely and provide a written assurance to help establish better understanding and effective cooperation.

The JAC said it respected and appreciated the assurances given by RIPPL and would continue to mobilise support for the company’s work. However, it cautioned that it would not remain a silent spectator if shortcomings or inefficiencies were detected, adding that RIPPL would be held responsible for any untoward incidents or consequences arising from such failures.

JAC members also raised technical concerns regarding the ongoing construction and questioned the company over what they described as prolonged inefficiency and disregard for the aspirations of the people. The committee stated that the public had lost patience and trust in the contractor over the years. However, following Murthy’s personal presence and assurances, the JAC had decided to extend cooperation to RIPPL once again, for the time being. It warned that failure to fulfil the commitments would prompt the committee to take the concerns of the people to higher authorities and initiate appropriate action.

Team Maverick.